How long will it take?

The Project Schedule will be agreed with you in advance by your Builder but may look something like this:- Week 1-2 Setting out, footings dug, and foundations poured Week 3-4 Building up to damp-proof course (DPC), drains installed, DPC installed and concrete floor structure put in Week 5 Building of external walls Week 6 Internal …

How long will it take? Read More »

Do I need to leave my home?

This depends entirely on the nature of your building project and whether it encroaches upon your day-to-day living space. However, it is not always necessary to move out for house extensions, garage and loft conversion. Your building contract should state that it is your responsibility to keep all children and animals safely away from the …

Do I need to leave my home? Read More »